- Location : Sevoke Railway Station
- Status of Work: Ongoing
- Client : IRCON / Gammon Engineers and Contractors Pvt Limited
- Value of Work : Rs 550 Crores
- Scope of Work : Construction of Tunnel T1 and T2 on Sevoke (West Bengal) to Rangpo (Sikkim) New Single line BG Railway Line Project
Salient Features
- T1 : 4203 Mtr.
- T2 : 867 Mtr.
- Finished Diameter : 7.2Mtr.
- Underground Excavation : 378954 Cum
- Shotcrete : 245172 Sqm.
- Structural steel support : 307 MT
- Lattice Girder : 1539 MT
- Lining Concrete : 69868 Cum