north east frontier railway (tunnel 12)

north east frontier railway (tunnel 12)
  • Kawnpui, Mizoram State
  • Northeast Frontier Railway
  • Completed
  • Rs.109.30 Crores
  • Scope of Work : Construction of Single Line BG Tunnel no. 12 (App. Length 1056 RM) at Km. 24.280 to 25.316 in between station Hortoki & Kawnpui

Salient Features

  • Method of Tunneling : NATM
  • Length of Tunnel : 1056 meters
  • Underground Excavation : 68,700 Cum (App.)
  • Open Excavation : 499000 Cum (App.)
  • Underground Shotcrete : 12,700 Cum (App.)
  • Underground Concrete : 16, 210 Cum (App.)
  • Steel : 2481.00 MT (App.)