- Location: Lingdok – East Sikkim
- Client: Haridwar Infrastructure Ltd (Greenko Group)
- Status of Work: Completed
- Value of Work: 251.09 Crores
- Scope of Work: Construction of Approach Roads, Intake Tunnel, Access Tunnels, De-silting Chambers, HRT, Gate Shafts, Silt Flushing Tunnel and other works in connection with Dikchu Hydroelectric Project and Construction of 35 Meters Height Concrete Dam and Intake Structure
Salient Features
- Height of Dam : 35.0 meters
- Length of Dam : 93.0 meters
- Type of Gates : Radial & Stop – Log
- No of Gates : 4 Nos.
- Dam Concrete : 69300.00 Cum (App.)
- Dam Reinforcement : 4500.00 MT (App.)
- Overflow blocks : 2 Nos.
- Non overflow blocks : 3 Nos.
- Intake : 390 meters X 5.4 meters
- HRT : 5500 meters X 5.4 meters
- SFT : 479.00 meters X 3.8 meters
- Desilting Chamber : 140m x 12m x15.5m
- No of Gate Shaft : 2 Nos.
- Length of Shaft : 10 meters & 22 meters
- Underground Excavation : 1,42,450.00 Cum (App.)
- Underground Concrete works : 23,500.00 Cum (App.)
- Concrete Lined Tunnel : 4.8 m. Dia X 3685 m. Length