Scope of Work

Work includes construction of silt check dam with rock fill, excavation in rock etc.

Salient Features

  • Rock filling : 53000 Cum
  • Excavation in Rock : 117000 Cum
  • Major part (Nearly 72%) of allotted job is completed with in three months.

Arun-3 Hydroelectric Project (900 MW)

Western Railway (Indore) – Tunnel No.1

Satna-Panna New BG Line Project

Likhu-4 Hydroelectric Project

Lower Solu Hydroelectric Project (82 MW)

Lower Solu Hydroelectric Project (82 MW)

Telengiri Irrigation Project (Spillway)

Telengiri Irrigation Project (Periphery Road)

Telengiri Irrigation Project (Earth Dam)

Telengiri Irrigation Project (Canal)

RET Irrigation Project (Spillway)

Dikchu Hydroelectric Project (Dam)

North East Frontier Railway (Tunnel 12)

North East Frontier Railway (Tunnel 21-22)

North East Frontier Railway (Tunnel 23)

Rengali Left Branch Canal

Dikchu Hydroelectric Project (Tunnels)

Kalpong Hydroelectric Project

Lower Suktel Irrigation Project (Spillway)

Larji Hydroelectric Project

Lumding-Silchar Gauge Conversion Project (Tunnels 5-6)

Lumding-Silchar Gauge Conversion Project (Tunnel 7)

Lower Suktel Irrigation Project (Earth Dam)

Cheligada Irrigation Project (High Level Bridge)