Location
Jeypore – Koraput – Odisha
Client
Odisha Construction Corporation
Date of Completion
Work in Progress
Scope of Work
Construction of Earth dam – Work includes earthwork excavation, embankment, filter blanket, riprap for earth dam in connection with Telengiri irrigation Project, TC Division, Orissa Construction Corporation Ltd. Barniput
Salient Features
- Length of Earth Dam : 600.00 meters
- Height of Dam : 43.00 meters
- Top width of Dam : 6.0 meters
- Bottom width of Dam : 200.00 meters
- Banking : 3600000 Cum
- Filters – Sand : 225000 Cum
- Filters – Aggregates : 32000 Cum
- Rock toe – Boulder : 35000 Cum
- Excavation in all classes : 405000 Cum