Telengiri Irrigation Project (Spillway)

Location

Jeypore – Koraput – Odisha

Client

Odisha Construction Corporation

Date of Completion

Work in Progress

Scope of Work

Construction of Spillway – Work includes earthwork excavation, reinforcement, concrete, etc in connection with Telingiri Irrigation Project

Salient Features

  • Span of Spillway : 113.0 meters
  • Height of Spillway : 43.0 meters
  • No of Gates : 3 Nos.
  • Spillway concrete : 396000 Cum
  • Spillway reinforcement : 2750.00 MT
  • Excavation in all classes : 623000 Cum

Arun-3 Hydroelectric Project (900 MW)

Western Railway (Indore) – Tunnel No.1

Satna-Panna New BG Line Project

Likhu-4 Hydroelectric Project

Lower Solu Hydroelectric Project (82 MW)

Lower Solu Hydroelectric Project (82 MW)

Telengiri Irrigation Project (Spillway)

Telengiri Irrigation Project (Periphery Road)

Telengiri Irrigation Project (Earth Dam)

Telengiri Irrigation Project (Canal)

RET Irrigation Project (Spillway)

Dikchu Hydroelectric Project (Dam)

North East Frontier Railway (Tunnel 12)

North East Frontier Railway (Tunnel 21-22)

North East Frontier Railway (Tunnel 23)

Rengali Left Branch Canal

Dikchu Hydroelectric Project (Tunnels)

Kalpong Hydroelectric Project

Lower Suktel Irrigation Project (Spillway)

Larji Hydroelectric Project

Lumding-Silchar Gauge Conversion Project (Tunnels 5-6)

Lumding-Silchar Gauge Conversion Project (Tunnel 7)

Lower Suktel Irrigation Project (Earth Dam)

Cheligada Irrigation Project (High Level Bridge)